PMP考试每天一练--PMP考试试题109
PMP考试试题一: To complete a process, phase, or project, which of the following must be approved? A. Budgets B. Deliverables C. Resources D. Schedules 若要完成一个过程,阶段或项目,必须获得下列哪一项的批准? A. 预算 B. 可交付成果 C. 资源 D. 进度表 PMP参考答案:B. 可交付成果 PMP答案解析:结束项目或阶段引言(4.6) P100 PMP考试试题二: You are in charge of a project developing a complex product that does not resemble anything your organization has done previously. You are using a resource to develop this product that is in high demand elsewhere in your organization. The project’s timeframe is very aggressive. In order to meet the schedule, only a limited amount of testing is done. Once the testing is completed, the resource is released. The product works fine when being tested, but in production, it performs poorly. This results in a substantial amount of rework and extra costs to reacquire the resource on an overtime basis. Which of the following BEST describes why this project had problems? A. Poor quality management. B. Poor reporting. C. Poor risk identification. D. Poor resource management. 你负责的项目是开发一个复杂的产品,而且你们公司之前没有做过类似的项目。你需要某一专业人员来开发这个产品,但这位专业人员在公司很抢手。项目的工期很紧,为了符合进度,测试部分只实施了一小部分,测试完成后,该专业人士就被调离了项目。测试的时候产品一切正常,但投入生产时就出了问题。这导致了大量的返工,并增加了额外成本,因为需要这位专业人员加班工作。以下哪项描述了可能产生此问题的原因? A.质量管理较差。 B.报告系统很差。 C.风险识别的较差。 D.资源管理较差。 审题: 此题的关键字为“测试部分只实施了一小部分,测试完成后,该专业人士就被调离了项目,需要这位专业人员加班工作”,隐含着风险问题。 定位: 规划过程组·项目人力资源管理·制定人力资源计划 解析: 项目对某一专业人员的依赖性较强,题干描述问题反映出人力资源计划不健全;为符合进度而只实施部分的测试,从而为生产时问题的发生埋下隐患。综合来看,问题的原因产生自资源管理较差。 PMP参考答案:D.资源管理较差。 |