PMP考试试题一:

An organization is considering developing and using a maturity model for project management. What is the major reason for using this type of model?

A. Help the organization improve its project processes and systems

B. Satisfy governmental regulations

C. Satisfy financial regulations

D. Help the organization compete in the global marketplace

一个组织正在考虑开发并使用一个成熟模型进行项目管理。使用这种模型的主要原因是什么?

A. 帮助组织改善项目过程和系统

B. 符合政府法规

C. 符合财务制度

D. 帮助组织在全球市场竞争

PMP参考答案:A. 帮助组织改善项目过程和系统

PMP答案解析:质量管理引言-组织项目管理成熟度模型OPM3 P228

PMP考试试题二:

Quality on your project must be as high as possible, yet this type of project is new for your company. Which of the following is the BEST thing to do?

A. Audit work as it is being completed to look for any needed improvements.

B. Improve your work authorization system.

C. Use cause and effect diagrams when there is a defect.

D. Make sure your staffing management plan is up to date.

你负责项目的质量越高越好,但这类型的项目对你公司来讲是全新的。以下哪项的做法是最佳的?

A.审核已完成的工作,看看是否有需要改善的地方。

B.改善你的工作授权系统。

C.出现问题时使用因果图进行分析。

D.确保你使用的人员配备管理计划是最新的。

审题: 此题的关键字为“质量越高越好、全新的”,持续提高质量。

定位: 监控过程组·质量管理·8.3 控制质量

解析: 答案A是一个持续改进的表述; 选项B、C、D都和题干情景要求不符。工作授权系统规定如何授权项目工作,以保证该工作由正确的组织、在正确的时间、以正确的顺序执行
,主要关注的是进度(选项B);而提高质量,有很多质量工具,需要根据不同情况使用,故选项C错误;人员配备管理计划(选项D)描述何时以及如何满足项目对人力资源的需求,是人力资源计划的一部分。

PMP参考答案:A.审核已完成的工作,看看是否有需要改善的地方。

阅读本文的人还阅读了:
2017年PMP考试相关注意事项
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP英文报名注意事项
PMP考试内容和PMP考试题型
PMP认证在国内的含金量
PMP考试成绩大秘密

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库