PMP考试试题一:

Progressive elaboration is a characteristic of projects that integrate the concepts of temporary and unique in project plan development, progressive elaboration also is terms of

A. Assumptions

B. Constraints

C. Project management information system

D. Organizational policies and procedures

渐进明细是结合了项目的一次性和独特性的特点。编制项目计划的过程中,渐进明细在以下哪个方面也是重要的:

A. 假设

B. 限制条件

C. 项目管理信息系统

D. 组织政策和程序

PMP参考答案:A. 假设

PMP答案解析:项目范围说明书-项目假设条件(5.3.3.1 ) P124

PMP考试试题二:

A project team is having difficulty communicating over long distances. There were 13 team members from two countries, and then five people from India were added. This is of concern to the project manager because:

A. Communications channels grow rapidly.

B. It will be harder to use reward power.

C. Communication blockers grow linearly.

D. Conflict can be increased with an increase in project priorities.

项目团队在远距离沟通上遇到了困难,13位团队成员来自不同的2个国家,后来又增加了5位来自印度的成员。这应该引起项目经理的关注,因为:

A. 沟通渠道迅速增加。

B. 使用奖励权力变得更困难。

C. 沟通阻碍者以直线的速度增加。

D. 项目优先级的增加导致冲突的增加。

审题: 此题的关键字为“远距离沟通上遇到了困难”和“增加了5为成员”,题干描述远程沟通的困难和人员增加的情况。

定位: 规划过程组.沟通管理·10.1.2 规划沟通管理: 工具和技术

解析: 此题主要解决的是沟通人员增加带来的沟通渠道增加的问题,选项A正确。 资源的增加一般不会增加使用奖励权力(选项B)的难度。选项C的描述本身就不正确。选项D在题干中没有涉及。

PMP参考答案:A. 沟通渠道迅速增加。

阅读本文的人还阅读了:
PMP英文报名注意事项
PMP考试内容和PMP考试题型
PMP认证在国内的含金量
PMP考试成绩大秘密
PMP报考条件和PMP报考流程
PMP考试难吗?

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库