PMP考试每天一练--PMP考试试题96
PMP考试试题一: The project manager is developing a project plan, on short notice project sponsor asks the project manager to create an initial rough estimate of project cost to satisfy requirements for the upcoming fiscal budget. The project manager uses which of the following for estimating the project cost? A. Bottom-up estimating B. Three-point estimating C. Analogous estimating D. Parametric modeling 项目经理正在制定一个项目计划。项目赞助人得知后,立即让项目经理针对项目成本开展初始粗略评估,以满足未来财政预算的需求。项目经理采用下列哪一项评估项目成本? A. 自下而上估算 B. 三点结算 C. 类比估算 D. 建立参数模型 PMP参考答案:C. 类比估算 PMP答案解析:估算活动历时工具:类比估算(6.5.2.2)P169 PMP考试试题二: After analyzing the status of your project, your determine that the earned value (EV) is lower than the planned value (PV). What should you expect as an outcome if this trend continues? A. The actual cost will be lower than planned. B. The estimate at completion will be lower than planned. C. The project will finish behind schedule. D. The project will finish below the original cost estimate. 分析完项目状况后,你发现项目的挣值(EV)低于计划值(PV)。如果这个趋势一直发展下去,结果将会如何? A.实际成本低于计划成本。 B.完工估算低于计划值。 C.项目完工日期将会落后预计进度。 D.项目完工的最终成本要比原先估算的要低。 审题: 此题的关键字为“挣值EV低于计划值PV”。 定位: 监控过程组.成本管理·7.4.2 控制成本: 工具和技术 解析: EV低于PV说明SV是处于负数状态,SV处于小于零时,是进度落后的表现,会出现项目进度(完工日期)落后预计进度的过程。C项满足此说法,其他选项都是描述的成本问题。 PMP参考答案:C.项目完工日期将会落后预计进度。 |