PMP考试试题一:

During a recent status review meeting for your project, one team member was critical of others and seemed to try to diminish their status on the team. This person was assuming which of the following destructive team roles?

A. Recognition seeker

B. Blocker

C. Aggressor

D. Dominator

在一个最近的项目状态评审会议上,一名团队成员对其他成员非常不满,而且贬低别人在团队中的地位,这个人属于下列哪项提及的破坏性团队角色?

A. 寻求赞誉者

B. 阻挡者

C. 攻击者

D. 独断者

PMP参考答案:C. 攻击者

PMP答案解析:团队中不同角色

PMP考试试题二:

A team member notifies the project manager that the activities comprising a work package are no longer appropriate. It would be BEST for the project manager to be in what part of the project management process?

A. Corrective action.

B. Integrated change control.

C. Monitoring and controlling.

D. Project closing.

一团队成员发现某一工作包的活动已经不再适用。此时,项目正处于哪个管理过程?

A.纠正措施。

B.整体变更控制。

C.监控过程组。

D.项目收尾。

审题: 此题的关键字为“哪个管理过程”,首先要明确下面的选项中哪个是管理过程。

定位: 框架.监控过程组

解析:

1、答案C是题干描述的情景。

2、选项A没有体现。

3、选项B项目经理首先要进行评估,然后才进入整体变更控制过程。

4、选项D仅仅是可能,但不是要问的目的。

PMP参考答案:C.监控过程组。

阅读本文的人还阅读了:
2017年PMP考试相关注意事项
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库