PMP考试每天一练--PMP考试试题-90
PMP考试试题一: In a fixed price (FP) contract, the fee or profit is: A. unknown. B. part of the negotiation involved in paying every invoice. C. applied as a line item to every invoice. D. determined with the other party at the end of the project. 在固定价格(FP)合同中,费用或利润是: A. 不知道的 B. 涉及支付每张发票的谈判的一部分 C. 作为排列项应用到每张发票 D. 和另外一方在项目期末一起确定的 PMP参考答案:A. 不知道的 PMP答案解析:合同类型(12.1.1.9)P362 PMP考试试题二: During project executing, the project manager is spending a lot of time solving problems that arise. It would be BETTER for the project manager to transfer his efforts to: A. Having the team solve the problems, thus freeing his time to hold more meetings. B. Executing the project management plan and making sure the quality management plan is viable. C. Identifying additional risks and following the risk management process. D. Performing sensitivity analysis on past problems and transferring them to other projects. 项目实施过程中,项目经理把主要时间放在解决问题上。其实,项目经理应该把精力转移到: A.让团队成员处理发生的问题,这样自己就会有很多时间来召开会议。 B.实施项目管理计划,并确保质量管理计划的可行性。 C.识别额外的风险,遵循风险管理程序。 D.实施敏感性分析,并将问题转移到其它项目上。 审题: 题干关键字“项目经理把主要时间放在解决问题上”,只有发现问题,找出问题根本原因,才能解决问题。 定位: 规划过程组.风险管理·11.6 控制风险 解析: 项目经理不需要把精力放在开会上,频繁的开会只会浪费项目的时间(选项A)。项目经理的角色是指导和控制,并不是直接的实施管理计划(选项B)。敏感性分析(选项D)在实施定量风险分析时已经完成了,现在是控制风险阶段。只有选项C应该解决问题的根本原因,在监控风险的时候要识别额外的风险,遵循风险管理程序。 PMP参考答案:C.识别额外的风险,遵循风险管理程序。 |