PMP考试每天一练--PMP考试试题-89

转载者:PMP团购网      发布时间:2017/5/3        点击: 2820

PMP考试试题一:

Which technology is usually used in identifying risks?

A. Resources histogram

B. Pareto Chart

C. Scatter chart

D. Delphi technique method

识别风险中最常用的技术是什么?

A. 资源直方图

B. 帕累托图

C. 散点图

D. 德尔菲技术

PMP参考答案:D. 德尔菲技术

PMP答案解析:识别风险的工具与技术(11.2.2)P324

PMP考试试题二:

A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response. Which of the following is the BEST thing for the project manager to do?

A. Document the new risks and continue the Plan Risk Responses process.

B. Make sure the project work is better understood.

C. Spend more time making sure the risk response are clearly defined.

D. Get more people involved in the Identify Risks process since risks have been missed.

项目经理正在制定风险应对计划。然而,每制定一个风险应对计划,就会导致另一新的风险产生。项目经理应该怎么做?

A.记录新风险,继续进行规划风险应对过程。

B.确保项目工作被更好地理解。

C.花点时间确认一下风险应对计划定义的是否清晰。

D.让更多的人参与到识别风险过程,以防止遗漏风险。

审题:题干关键字“每制定一个风险应对计划,就会导致另一新的风险”,指的是次生风险。

定位:规划过程组.风险管理·11.5.2 规划风险应对

解析: 此题描述的是次生风险问题。在完成规划风险应对过程中识别次生风险对项目是有益的。对于次生风险不能忽视,需要记录下来,加入日后的观察清单,以便日后审查。

PMP参考答案:A.记录新风险,继续进行规划风险应对过程。

阅读本文的人还阅读了:
PMP审查常见问题
PMI为什么不公布PMP题目和PMP考试答案
PMP报考条件和PMP报考流程
PMP考试监考机构和报名机构
北京PMP培训团购
上海PMP培训团购
2017年PMP考试时间安排
2017年PMP考试相关注意事项
2017年PMP报考条件和报名流程

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库