PMP考试每天一练--PMP考试试题-84
PMP考试试题一: Emphasizing which of the following activities has affected the most important to cost of quality? A. prevention B. Appraisal C. Measurement D. Rework 强调下列哪一项活动对质量成本会产生最重要的影响? A. 预防 B. 评估 C. 测量 D. 返工 PMP参考答案:A. 预防 PMP答案解析:质量管理引言 P228 PMP考试试题二: The project manager has completed the Plan Risk Responses process, and has identified risk response strategies with the team. The team’s manager has asked for the amount of risk reserves needed for the project. What is the FIRST thing the project manager should do? A. Create the risk reserves. B. Prioritize the list of risks. C. Create the overall risk rating for the project. D. Determine secondary risks. 项目经理已经完成了规划风险应对过程,并与团队一起识别了风险应对策略。团队的经理想知道项目的风险储备量是多少。项目经理首先应该做什么? A.制定风险储备。 B.制定风险优先级清单。 C.制定项目整体风险等级。 D.确定次生风险。 审题:根据题干,已经进行了规划风险应对,考虑接下来首先应该做什么以获得项目的风险储备量。 定位:规划过程组·风险管理·11.5.2 规划风险应对 解析:风险应对策略制定之后,另外一影响风险储备的因素就是确定次生风险。制定风险储备应在确定次生风险后,所以选项A错误。制定风险优先级及风险等级都在定性风险分析中已经确定,所以选项B、C错误。 PMP参考答案:D.确定次生风险。 |