PMP考试试题一:

Emphasizing which of the following activities has affected the most important to cost of quality?

A. prevention

B. Appraisal

C. Measurement

D. Rework

强调下列哪一项活动对质量成本会产生最重要的影响?

A. 预防

B. 评估

C. 测量

D. 返工

PMP参考答案:A. 预防

PMP答案解析:质量管理引言 P228

PMP考试试题二:

The project manager has completed the Plan Risk Responses process, and has identified risk response strategies with the team. The team’s manager has asked for the amount of risk reserves needed for the project. What is the FIRST thing the project manager should do?

A. Create the risk reserves.

B. Prioritize the list of risks.

C. Create the overall risk rating for the project.

D. Determine secondary risks.

项目经理已经完成了规划风险应对过程,并与团队一起识别了风险应对策略。团队的经理想知道项目的风险储备量是多少。项目经理首先应该做什么?

A.制定风险储备。

B.制定风险优先级清单。

C.制定项目整体风险等级。

D.确定次生风险。

审题:根据题干,已经进行了规划风险应对,考虑接下来首先应该做什么以获得项目的风险储备量。

定位:规划过程组·风险管理·11.5.2 规划风险应对

解析:风险应对策略制定之后,另外一影响风险储备的因素就是确定次生风险。制定风险储备应在确定次生风险后,所以选项A错误。制定风险优先级及风险等级都在定性风险分析中已经确定,所以选项B、C错误。

PMP参考答案:D.确定次生风险。

阅读本文的人还阅读了:
2017年PMP考试时间安排
2017年PMP考试相关注意事项
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库