PMP考试试题一:

During the planning phase of a project, the project manager expects a delay due to procurement. The project manager continues to plan for the impact of this delay and alternative strategies. The possible delay in procurement could be defined as which of the following?

A. risk

B. Assumption

C. Constraint

D. Dependency

在项目的计划编制阶段,项目经理预期到可能由于采购原因而导致延期。项目经理仍将继续计划该延期所产生的影响以及替代战略。在采购阶段可能产生的延期可被定义为哪一项?

A. 风险

B. 假设

C. 制约因素

D. 依赖关系

PMP参考答案:A. 风险

PMP答案解析:风险的定义 P310

PMP考试试题二:

During the Identify Risks process, a project manager made a long list of risk identified by all the stakeholders using various methods. He then made sure that all the risks were understood and that triggers had been identified. Later, in the Plan Responses process, he took all the risks identified by the stakeholders and determined ways to mitigate them. What has he done wrong?

A. The project manager should have waited until the Perform Qualitative Risk Analysis process to get the stakeholder involved.

B. More people should be involved in the Plan Risk Responses process.

C. The project manager should have created workarounds.

D. Triggers are not identified until the Identify Risk process.

识别风险过程中,项目经理制定了一份由干系人通过各种方式识别出来的风险清单,于是他认为了解了所有风险,识别了所有风险诱发因素。在后来的风险应对过程,他就针对干系人识别出的风险确定了缓解措施。他错在哪里?

A. 项目经理应该等到实施定性风险分析过程结束后在开始制定应对策略,因为定性风险分析过程会涉及干系人。

B. 应该有更多的人参与规划风险应对过程。

C. 项目经理应该制定权变措施。

D. 风险诱发因素只有在识别风险过程中才能识别出来。

审题: 根据题干,该题考的是风险管理中规划风险应对需哪些人参与。

定位: 规划过程组·风险管理·11.5 规划风险应对

解析: 所有风险应对负责人及其他相关人都必须参与风险应对规划过程。

PMP参考答案:B. 应该有更多的人参与规划风险应对过程。

阅读本文的人还阅读了:
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库
PMP一般的学习流程简介
PMP项目管理考试费用变更

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库