PMP考试试题一:

The project team is required to comply with government regulations and union contracts. The project manager has identified the strategy for its implementation. Which plan should be updated with this strategy?

A.Staffing management plan

B.Risk management plan

C.Project management plan

D.Communication management plan

项目团队被要求遵守政府法规和劳工合同。项目经理已经确定了实施战略。下列哪一项计划应跟随战略更新?

A.人员配备管理计划

B.风险管理计划

C.项目管理计划

D.沟通管理计划

PMP参考答案:A.人员配备管理计划

PMP答案解析:人员配备管理计划-合规性 (9.1.3.1) P265

PMP考试试题二:

You are having difficulty estimating the cost of a project. Which of the following BEST describes the most probable cause of your difficulty?

A.Inadequate scope definition.

B.Unavailability of desired resources.

C.Lack of historical records from previous projects.

D.Lack of company processes.

你在做成本估算时遇到了困难,以下哪项是出现困难的最可能原因?

A.缺乏确定的范围。

B.没有提供预期的资源。

C.缺乏以前项目的历史数据。

D.公司缺少流程。

审题:造成成本估算困难,可以理解为输入出现了问题。回忆成本估算过程的几个输入,用排除法找到对该过程影响最大、最根本的因素。

定位:规划过程组·成本管理·估算成本

解析:

1、项目的历史数据和流程都属于组织过程资产,这项输入只是估算的参考数据,可能会增加成本估算的难度,但不会是导致困难的根本原因,因此C、D不对。

2、没有获得预期的资源可能会导致估算精度不够,但是依然会有一个大概的答案,因此B不对。

3、算的前提是范围明确。因此答案为A。如果范围定义不清楚,也就是没有一个确定的范围基准,那么将无法进行任何估算。

PMP参考答案:A. 缺乏确定的范围。

阅读本文的人还阅读了:
PMP考试内容和PMP考试题型
PMP认证在国内的含金量
PMP考试成绩大秘密
PMP报考条件和PMP报考流程
PMP考试难吗?
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库
PMP一般的学习流程简介

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库