PMP考试每天一练--PMP考试试题-77

转载者:PMP团购网      发布时间:2017/4/5        点击: 2233

PMP考试试题一:

All of the following are the responsibility of a project manager EXCEPT?

A. Maintain the confidentiality of customer confidential information.

B. Determine the legality of company procedures.

C. Ensure that a conflict of interest does not compromise the legitimate interest of the customer.

D. Provide accurate and truthful representations in cost estimates.

下列哪项不是项目经理的责任?

A. 为客户的信息保密

B. 决定公司的程序是否合法

C. 确保利益冲突不会损害客户的合法利益

D. 在估算成本中提供准确可信的说明

PMP参考答案:B. 决定公司的程序是否合法

PMP答案解析:项目经理的责任

PMP考试试题二:

A project manager is working on a major new product development project when a risk occurs that does not have a risk response plan. What should the project manager do?

A. Hold a risk reassessment and plan a workaround.

B. Inform management and communicate the new risk to the team.

C. Communicate the planned response to the stakeholder.

D. Use some of the reserves to accommodate the risk.

项目经理负责的新产品开发项目发生了一项风险,这项风险之前没有制定应对计划。项目经理应该怎么做?

A. 进行风险评估,并制定权变措施。

B. 将新风险通知给管理层。

C. 和干系人商谈应对计划。

D. 动用一些储备。

审题: 本题的关键字是“发生了一项风险”和“没有制定应对计划”,显然是与风险管理有关,考察的是当未识别出的风险发生之后,项目经理应该如何应对。

定位: 监控过程组·风险管理·11.6 控制风险

解析: 这里要借鉴控制风险中用到的输入输出和工具。在项目过程中监控到新的风险发生,应该先评估风险的影响(工具)。同时由于没有应对计划,应该及时指定权变措施(输出)。

PMP参考答案:A. 进行风险评估,并制定权变措施。

阅读本文的人还阅读了:
PMP项目管理考试费用变更
PMP试题权重比例及评分规则
PMP审查常见问题
PMI为什么不公布PMP题目和PMP考试答案
PMP报考条件和PMP报考流程
PMP考试监考机构和报名机构

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库