PMP考试每天一练--PMP考试试题-76

转载者:PMP团购网      发布时间:2017/4/3        点击: 2572

PMP考试试题一:

Which of the following describes the amount of individual resources required for an existing schedule during specific time periods?

A. Resource histogram

B. Resource loading

C. Resource leveling

D. Resource planning

下列哪一项描述了现有进度表的特定时间段内对个别资源的需求量?

A. 资源直方图

B. 资源负荷

C. 资源平衡

D. 资源规划

PMP参考答案:A. 资源直方图

PMP答案解析:人力资源计划-资源直方图( 9.1.3.1 ) P266

PMP考试试题二:

During the completion of the project work, a project manager wants to ensure that the quality of the end product is acceptable. The BEST way to do this is by:

A. Checking quality against the standards set in the quality management plan.

B. Identifying the quality standards you want then end product to meet.

C. Performing cost-benefit analysis.

D. Determining the cause of a problem using a fishbone diagram.

在项目工作完成阶段,项目经理确保最终产品的质量被接受。最佳做法是:

A.将实际完成产品的质量与质量管理计划中规定的质量标准进行核实。

B.识别最终产品需要满足的质量标准。

C.实施成本收益分析。

D.使用鱼骨图来确定问题的原因。

审题: 关键字是“工作完成阶段”和“确保最终产品质量被接受”。 考察的是项目经理要以什么输入为依据,通过什么工具“确保最终产品的质量被接受”。

定位: 监控过程组·质量管理·8.3 控制质量

解析: B是规划质量管理需要做的内容,属于规划过程组。C是规划质量管理的工具。这两项都应该早于这个阶段完成。D鱼骨图只是质量控制的其中一种工具,但不是用于最终产品的质量检查。

PMP参考答案:A.将实际完成产品的质量与质量管理计划中规定的质量标准进行核实。

阅读本文的人还阅读了:
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库
PMP一般的学习流程简介
PMP项目管理考试费用变更

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库