PMP考试每天一练--PMP考试试题-74
PMP考试试题一: What is the goal of a quality audit on a project? A. Deliver higher quality products for the same price. B. Rate the quality of a process C. Identify inefficient and ineffective processes. D. Report project quality to the sponsor. 项目质量审计的目标是什么? A. 以同样的价格提供更高质量的产品。 B. 对过程的质量评级 C. 识别低效率和无效的过程 D. 将项目质量报告给发起人 PMP参考答案:C. 识别低效率和无效的过程 PMP答案解析:质量审计目的 (8.2.2.2)P247 PMP考试试题二: John is managing a mufti-phase project and needs to validate the previous phase's assumptions and decisions in order to determine if the business needs for the project still exist. Referring to the scenario above, which one of the following processes does John need to follow to accomplish this goal? A. Monitoring and Controlling Process B. Initiating Process C. Closing Process D. Executing Process 约翰管理一个多阶段的项目,需要验证前一阶段的假设和决策,以便判断项目的商业需求是否依然存在。完成这一目标,约翰处于哪一个过程? A. 监控过程。 B. 启动过程。 C. 收尾过程。 D. 执行过程。 审题: 关键词“多阶段”和“验证前一阶段的假设和决策”和“以便判断项目的商业需求”一般是项目启动时要做的工作,但是整个项目完成了几个阶段了,是否仍然是启动过程呢? 定位: 启动过程组·项目管理框架·3.3 启动过程组 解析: 确定前一阶段的工作已确认是否可以进入后已阶段,按照各阶段为一个项目的原则,约翰完成的目标是在项目的启动阶段。 PMP参考答案:B. 启动过程。 |