PMP考试每天一练--PMP考试试题-72

转载者:PMP团购网      发布时间:2017/3/27        点击: 2703

PMP考试试题一:

Company ABC is evaluating three consulting companies to find a consultant to perform professional services. They request information on how the three consulting companies allocate fringe benefits to their clients. What type of cost is company ABC asking about?

A. Variable

B. Fixed

C. Direct

D. Indirect

ABC公司正在对三家咨询公司进行评估,希望选出一名顾问来做专业的服务。他们要求三家公司提供如何向客户分配边际利润的信息。ABC公司询问的这类成本属于:

A. 可变成本

B. 固定成本

C. 直接成本

D. 间接成本

PMP参考答案:D. 间接成本

PMP答案解析:成本分类

PMP考试试题二:

A project is facing a major change to its project deliverables. If the project manager is involved in determining which quality standards are relevant to the change,the project manager must be involved in:

A. Quality management.

B. Perform Quality Assurance.

C. Plan Quality.

D. Quality Control.

项目经理正面临一个很大的变更。如果项目经理需要参与决定与该变更相关的质量标准,那么,他必须进行:

A. 质量管理。

B. 质量保证。

C. 质量规划。

D. 质量控制。

审题:此题有很大的迷惑性,题目表面好像是关于变更的内容,根据关键字“参与决定与该变更相关的质量标准”,实际上是在说质量规划,因为质量控制是与其他阶段并行开展。

定位:规划过程组·项目质量管理·8.1 规划质量管理

解析:变更了,不是在执行和监控阶段才变更吗?是的。但是,项目的各个阶段是可能交叉的,也有可能回退。对变更的质量标准的分析,又回到了质量规划阶段,因为这是确定质量标准的必经之路。

PMP参考答案:C. 质量规划。

阅读本文的人还阅读了:
2017年PMP报考条件和报名流程
2017年PMP考试时间及全国考点
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库
PMP认证在国内的含金量
PMP考试成绩大秘密
PMP报考条件和PMP报考流程

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库