以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练--PMP考试试题-65

转载者:PMP团购网      发布时间:2017/3/10        点击: 2173

PMP考试试题一:

A number of tools and techniques are helpful in integrated change control, if you want to assess whether variances form the plan require corrective action, you should use___

A. Configuration management software

B. A project management information system

C. Project status review meetings

D. Performance measurement techniques

大量的工具和技术对于整合变更控制的过程是非常有帮助的。如果你想评估偏离了原计划的项目是否需要矫正行为,你应该使用

A. 范围变更管理软件

B. 一个项目管理信息系统

C. 项目状态评估

D. 绩效测评技术

PMP参考答案:D. 绩效测评技术

PMP答案解析:进度控制工具:绩效审查(6.7.2.1) P188

PMP考试试题二:

Your boss is worried about the project schedule. There is a critical deliverable due to the federal government in two weeks. If you miss the deliverable, you could lose the entire contract. To help reduce the boss’s stress you show him the earned valued calculations you just completed. They show your cost performance index(CPI) is 1.25, your actual cost (AC)is US$400 million, and your planned value(PV) is US$490million. Should your boss be comfortable?

A. Yes, your SV is $10million.

B. No, your CPI is too high.

C. He needs more data.

D. Yes, your SPI is 1.05.

你老板正担心项目的进度,因为涉及两周内完成一个关于联邦政府的关键可交付物。如果到期交付不了,那么将会失去整个合同。为了不让你的老板担心,你给他计算了挣值。CPI是1.25,
AC是400,000,000美元,PV是490,000,000美元。你老板对项目会放心吗?

A. 是的。因为SV是10,000,000美元。

B. 不会。因为CPI太高了。

C. 他还需要更多的数据。

D. 是的。因为SPI是1.05。

审题: 此题的关键字为“项目进度”和“关键可交付物”,意思就是老板关心的即有进度也有关键可交付物,所以先要确定进度偏差,再确定关键可交付物是否完成。

定位: 监控过程组·时间管理·6.7.2 控制进度:工具与技术

解析:

1、 尽管SV是10,000,000美金,但并不意味着项目活动按照进度进行。项目经理应该知道影响关键可交付成果的活动是否一切在按照进度计划执行。EVM是计算项目的发展趋势的,你还需要更多的详细信息。

2、 选项B不正确,因为不能通过CPI确定项目进度问题。

3、 选项D错误,因为SPI是1.02,而不是1.05。 从题干可以计算SPI和CPI,项目进度和成本都在控制范围之内。但是从SPI看,进度并未提前很多,依然非常吃紧。而且考虑未来的风险,如果我们是老板,我们也依然不会放心。

PMP参考答案:C. 他还需要更多的数据。

阅读本文的人还阅读了:
PMP考试内容和PMP考试题型
如何参加PMP考试?
PMP项目管理考试费用变更
PMP考试题库
PMP一般的学习流程简介
PMP项目管理考试费用变更
PMP试题权重比例及评分规则

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库