PMP考试试题一:

You are taking over a project during the planning process group and discover that six individuals have signed the project charter. Which of the following should MOST concern you?

A. Who will be a member of the change control board

B. Spending more time on configuration management

C. Getting a single project sponsor

D. Determining the reporting structure

项目进入了规划阶段你才接手,并且发现六个人已经签署了项目章程。以下你最应该关注哪项?

A. 变更控制委员会会员是谁。

B. 花更多的时间进行配置管理。

C. 使项目有一个项目发起人。

D. 确定汇报结构。

PMP参考答案:B. 花更多的时间进行配置管理。

PMP答案解析:整体变更控制流程 (4.5)P94

PMP考试试题二:

A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of spilled rock per day. In which of the following does the project manager document quality control, quality assurance, and quality improvements for this project?

A. Quality management plan.

B. Quality policy.

C. Control charts.

D. Project management plan.

铁路设备公司的项目经理和他的团队接到任务设计一台机器用来给火车车厢装载石头,该设计允许2%的溢漏量,也就是每天累计的溢漏量超过两吨。那么,项目经理将质量控制、质量保证和过程改进的文档记录在:

A. 质量管理计划。

B. 质量政策。

C. 控制图。

D. 项目管理计划。

审题: 此题的关键字为“。。。质量控制、质量保证和过程改进的文档记录在。。。”,讲的是制定质量管理计划的事。

定位: 规划过程组·质量管理·8.1.3规划质量管理:输出

解析:

1、质量管理计划是规划质量的输出。质量管理计划包括项目的质量控制、质量保证和持续过程改进。

2、B质量政策属于组织过程资产;C控制图用来确定一个过程是否稳定或者是否具有可预测的绩效,有上下限, 是一种工具与技术;D项目管理计划范围相对于“质量控制、质量保证和过程改进的文档”范围太广。

PMP参考答案:A. 质量管理计划。