PMP考试试题一:

All the techniques described below can be used to keep a meeting focused except:

A. Recall agenda items/purpose of meeting

B. Summarize discussion periodically

C. Encourage pursuit of interesting new ideas

D. Rephrase unclear ideas presented by group members

下述技术可以用来保持会议焦点集中,除了:

A. 回顾议程条款/会议的目的

B. 阶段性地总结讨论过的内容

C. 鼓励追求有趣味的新想法

D. 重新描述小组成员提出的措辞不明的想法

PMP参考答案:C. 鼓励追求有趣味的新想法

PMP答案解析:焦点小组会议( 5.2.2.2 )P114

PMP考试试题二:

During its first winter, a multi-year construction project experienced weather-related schedule delays that all the local parties involved described as typical for this area. What should the project manager do to integrate this information into the project schedule?

A. Lengthen the estimated activity duration for all activities scheduled to occur the following winter.

B. Reevaluate the schedule to determine the potential impact.

C. Leave the current project schedule unchanged and work the issues as they arise next year.

D. Make changes to the project management plan in order to maintain the current project schedule.

需要历时多年的建设项目进入第一个冬季时遭遇了天气问题,导致进度延迟。所有当地建设方说这是该地典型的天气。项目经理为了将天气问题考虑到进度计划中,他应该怎么做?

A.将所有发生在冬季的活动的历时延长。

B.重新评估进度计划以确定潜在的影响。

C.保持现有进度计划不变,在下个冬季发生问题时再解决。

D.变更项目管理计划,以便保持现有的进度计划。

审题: 此题的关键字为“天气问题,导致进度延迟”,讲的是进度变更与风险的问题。

定位: 规划过程组·时间管理·6.6 制定进度计划&11.2.1.3 识别风险:输入

解析:

1、现在进度约束条件改变了——冬季天气问题,合理地评估天气对进度所造成的影响,重新调整项目进度计划,这样会必然会造成进度管理计划的变更。

2、进度管理计划是识别风险的输入,会影响到风险的识别,需要重新识别风险。

3、重新评估项目进度计划,可以合理地估算天气对进度所造成的影响,同时可以进行合理风险分析。

PMP参考答案:B.重新评估进度计划以确定潜在的影响。