PMP考试试题一:

The summary milestone schedule and summary budget have just been determined. What project management process group are you in?

A. Initiating

B. Planning

C. Executing

D. Monitoring and controlling

已经确定了总体里程碑计划和总体预算,那么项目处于哪个管理过程组?

A. 启动

B. 规划

C. 执行

D. 监控

PMP参考答案:A. 启动

PMP答案解析:项目章程(4.1.3.1)P71

PMP考试试题二:

A project manager meets with a resource manager and asks to move resources from project A to project B. What is the MOST likely reason for this request?

A. A problem has caused delay beyond the project manager’s ability to control.

B. Project A has become higher priority within the organization.

C. An activity has taken longer than planned.

D. An activity was missed because a work breakdown structure was not created.

项目经理会见资源经理,希望把项目A的资源借调给项目B。发生此问题的最可能的原因是什么?

A. 发生了问题导致项目进度延后,进度落后的程度超出了项目经理控制能力。

B. 项目A在公司开始拥有更高的优先级。

C. 完成活动的时间比预期的要长。

D. 没有制定工作分解结构,导致某项活动遗漏。

审题: 此题的关键字为“资源经理”和“资源借调”,意思就是什么原因下超出了项目经理能自己处理的范围需要求助于资源经理,考查的是项目执行过程中哪些情况是超出项目经理能处理的能力之外的。

定位: 执行过程组·整合管理·4.3 指导与管理项目工作

解析:

1、 如果项目A拥有了更高的优先级,那么资源就会直接分给项目A,而非借调了,选项B不正确。

2、 如果C和D的情况发生,应该在项目的约束条件内解决,而不是直接去移动资源。

答案:A. 发生了问题导致项目进度延后,进度落后的程度超出了项目经理控制能力。

阅读本文的人还阅读了:
考了PMP对提升待遇有帮助吗?
PMP有效期多久?
PMP考试题型是什么?
全球有多少PMP?
PMP认证是什么?
英语不好可以考PMP吗?
PMP培训视频哪里可以下载?
高中或以下学历可以考PMP吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库