PMP考试每天一练--PMP考试试题-21

转载者:PMP团购网      发布时间:2016/10/29        点击: 2944

PMP考试试题一:

The project is close to completion. All project deliverable have been accepted by the stakeholders. The program manager has asked the project manager to take on another project. All external contracts have been met and all the contracts closed. What should the project manager do?

A. Announce the project is closed and move to the new project.

B. Ensure that all procedures to transfer the project’s products and service to production are in place.

C. Conduct an external review of the project by a team of experts.

D. Ensure the remaining project activities are transferred to the new project

项目已完成,所有项目可交付成果都已经获得项目干系人的验收。所有外部合同都已经满足,所有合同已经结束。项目集经理让项目经理处理另外一个项目,项目经理应该做什么?

A. 宣布项目结束,并转到管理新项目。

B. 确保将项目产品或服务转到生产的所有程序均以就位

C. 由专家组对项目执行外部审查。

D. 确保剩余的项目活动转到新项目中

PMP参考答案:C. 由专家组对项目执行外部审查。

PMP答案解析:结束采购-工具与技术-采购审计 (12.4.2.1)P388

PMP考试试题二:

下列各项除哪项外,是有关“基层估算”(grassrootsestimate)的正确陈述?

a.其准确率范围为-5%到+10%

b.也称做工程估算

c.它主要用于工作分解结构的第一级

d.可能需花费数月时间编制它

PMP正确答案:c.它主要用于工作分解结构的第一级