PMP考试每天一练--PMP考试试题-19
PMP考试试题一: Due to a lack of an employee training and proper production control, defects in a production run caused rework which cost the company $250,000. How much of this cost is directly attributable to the employees on the production line? A. $75,000 B. $37,500 C. $212,500 D. $145,000 由于员工缺乏培训和适当的生产控制,生产过程中发现了错误需要返工解决。返工成本为$250,000。其中员工负有责任的成本为 A. $75,000 B. $37,500 C. $212,500 D. $145,000 PMP参考答案:B. $37,500 PMP答案解析:质量责任 PMP考试试题二: 统计抽样是实施质量控制的一种方法,用以确定项目的某个组成部分或产品符合要求的程度。其最大优势在于它____。 a.无须耗用大量资源 b.足够准确,且取样不足1% c.为得出对总体的令人满意的推断, d.只有当发现最终产品出现问题时,无须对组成部分进行100%的检查或者顾客退货时,才需要进行抽样 PMP正确答案:C |