PMP考试练习--合同与采购管理(21-25题)
合同与采购管理-PMP考试章节练习(21-25题) 21. A contractor is hired on a CPFF basis. The estimated cost of the contract is $100,000; however, at completion the contract costs total $125,000. The agreed upon percentage profit paid to the contractor is 15%. How much will the contractor receive? 承包商在CPFF 的条件下受雇,合同估计的成本是$100,000,但是项目实际完成时花费了$125,000 。已经同意的支付给承包商的利润率是15%。承包商将得到多少? 22. A contractor is hired to construct a storage shed. The performance cost is $1,500, with $6,500 in materials, and a 50% incentive fee. The contractor completes the storage shed in 130 hours, with a materials cost of $6,200. The contractor is paid $7,850 at completion. What type of contract is being used for this project? 一个承包商受雇建造一个存货仓库。执行成本是$1,500,原料是$6,500,以及50%的激励酬金。承包商完成工程用了130 个小时,消耗了$6,200 的材料。在完工时,承包商获得$7,850 的报酬。这个项目中使用了哪种合同形式? 23. A company is going into the procurement on a project and must decide what type of contract to use. This decision is made in what phase of the Acquisition Process? 公司在项目中即将开采采购并且必须决定采用何种合同形式,这一决定是在采购过程的那个阶段作出? 24. When a project’s contract is not fully executed caused by a direct fault of the seller, the owner is entitled to seek damages. What condition best describes this occurrence? 当项目合同由于卖方直接过错而未能完全履行时,业主有权寻求赔偿金。哪个条款最好地描述了此种情形? 25. Administrative closure should take place: 项目管理收尾应该发生在: PMP考试练习答案(合同采购):21-25 ADABE |