PMP考试练习--合同与采购管理(21-25题)

转载者:PMP团购网      发布时间:2014/11/27        点击: 2965

合同与采购管理-PMP考试章节练习(21-25题)

21. A contractor is hired on a CPFF basis. The estimated cost of the contract is $100,000; however, at completion the contract costs total $125,000. The agreed upon percentage profit paid to the contractor is 15%. How much will the contractor receive?
A. $140,000
B. $15,000
C. $115,000
D. $18,750

承包商在CPFF 的条件下受雇,合同估计的成本是$100,000,但是项目实际完成时花费了$125,000 。已经同意的支付给承包商的利润率是15%。承包商将得到多少?
A. $140,000
B. $15,000
C. $115,000
D. $18,750

22. A contractor is hired to construct a storage shed. The performance cost is $1,500, with $6,500 in materials, and a 50% incentive fee. The contractor completes the storage shed in 130 hours, with a materials cost of $6,200. The contractor is paid $7,850 at completion. What type of contract is being used for this project?
A. CPFF
B. CPPC
C. FFP
D. CPIF

一个承包商受雇建造一个存货仓库。执行成本是$1,500,原料是$6,500,以及50%的激励酬金。承包商完成工程用了130 个小时,消耗了$6,200 的材料。在完工时,承包商获得$7,850 的报酬。这个项目中使用了哪种合同形式?
A. CPFF
B. CPPC
C. FFP
D. CPIF

23. A company is going into the procurement on a project and must decide what type of contract to use. This decision is made in what phase of the Acquisition Process?
A. plan purchase and Acquisitions
B. plan contracting
C. request seller responses
D.select seller

公司在项目中即将开采采购并且必须决定采用何种合同形式,这一决定是在采购过程的那个阶段作出?
A. 采购规划
B. 发包规划
C. 询价
D. 卖方选择

24. When a project’s contract is not fully executed caused by a direct fault of the seller, the owner is entitled to seek damages. What condition best describes this occurrence?
A.A contract that was not written according to laws governing the state or municipality where the contract was issued or performed
B.The condition describes a breach of the contract
C.Force majeure
D.Implied warranty

当项目合同由于卖方直接过错而未能完全履行时,业主有权寻求赔偿金。哪个条款最好地描述了此种情形?
A.依据合同签署和执行所在地国家和当地政府的法律的非书面合同
B.描述违约的条款
C.不可抗力
D.暗示保证

25. Administrative closure should take place:
A. after the project is complete
B. at the end of each phase of the project to ensure important information is not lost
C. after the final invoices have been processed
D. when a project has been terminated
E. BandD

项目管理收尾应该发生在:
A. 在项目完成后
B. 在项目的每一个阶段结束后,以确保重要的信息不至于丢失
C. 在最后一张发票开出来后
D. 项目被终止时
E. B 和D

PMP考试练习答案(合同采购):21-25 ADABE