项目风险管理-PMP考试章节练习(11-15题)11. The project budget has been finalized. Additional work has been discovered that was not planned for in the budget or project scope. Where could the funds be found to cover the newly discovered work item?
A. Contingency reserve
B. Project profit
C. Management reserve
D. Abandoning fund
项目预算已经完成。但是发现有额外的工作没有计算到预算或项目范围中。在什么样的资金能够包含最近发现的工作内容?
A. 应急备用金
B. 项目利润
C. 管理备用金
D. 废弃资金
12. As a means of deflecting project risk, the project manager should consider:
A. not implementing the project
B. the use of another project manager
C. establishing a sunk cost fund
D. ignoring the risk
E. insurance whenever possible
作为风险转移的一种方法,项目经理应该考虑:
A. 不实施项目
B. 启用另一个项目经理
C. 建立沉淀资金
D. 忽略风险
E. 需要时上保险
13. Which phase of the project life cycle has the highest uncertainty?
A. Conceptual
B. Planning
C. Design
D. Implementation
E. Termination
项目生命周期中哪个阶段有最大的不确定性?
A. 概念
B. 计划
C. 设计
D. 实施
E. 中止
14. Which of the following fit the category of external risks?
A. Project delays, budget underruns, movement of city utilities
B. Regulatory, currency changes, taxation
C. Natural disasters, regulatory, design
D. Inflation, design, social impact
E. Political unrest, budget overruns, size and complexity of the project
下面哪种分类属于外部风险?
A. 项目延迟,预算超支,城市设施的迁移
B. 规章制度,货币变化,税收
C. 自然灾害,规章制度,设计
D. 通货膨胀,设计,社会方面的影响
E. 政治动荡,预算超支,项目的大小和复杂性
15. In the area of legal risks, there are two reasons for licensing of projects. One reason is for revenue generation by the community: the other is for:
A. harassment of the project manager
B. bureaucratic interest in the project
C. public safety of the product
D. monitoring of the project schedule
E. identification of the project manager
在法律风险方面,有两个原因给项目发许可证。一个是收益由公众产生,另外一个是:
A. 不让项目经理闲着
B. 官僚的原因
C. 产品对公众的安全
D. 项目进度的监测
E. 项目经理的识别
PMP考试练习答案(风险管理):11-15 CEABC