PMP考试题库(项目风险管理)1-5题

转载者:PMP团购网      发布时间:2014/11/1        点击: 3127

项目风险管理--PMP考试章节练习(1-5题)

1. Risk management includes the processes concerned with_______, __________, and _________ uncertainties during the project’s life cycle.
A. Utilizing, supporting, and determining
B. Quantifying, controlling, and monitoring
C. Analyzing, monitoring, and response initialization of
D. Costing, planning, and constraining
E. Identifying, analyzing, responding to

风险管理包括________ 、_________ 和__________ 在项目的生命周期里的不确定性:
A. 利用、支持和判断
B. 质化、控制和监控
C. 分析、监控和对启动反应的
D. 成本、计划和限制
E. 识别、分析和应对

2. PMI states that there are two risk types: business and insurable. Which of the following are considered are considered insurable risks?
A. Employee replacement costs
B. Opportunity cost
C. Sunken costs
D. Damage caused by a bonded contractor
E. A andD

PMI 认为存在两种类型的风险:商业的和可保险的。下面哪个被认为是可保险的风险?
A. 员工替换成本
B. 机会成本
C. 沉淀成本
D. 由债券作担保的承包商引起的损失
E. A 和D

3. The three attributes of project risk are________, _________, and ________.
A. What might happen, who it happens to, and how much will it cost
B. Notification, frequency of relevant events, probability of occurance
C. Risk cost, quality, control
D. Quality, risk planning, total number of risk events
E. Risk event, probability occurrence, the amount at stake

项目风险具有三个属性:__________ 、___________ 和___________ 。
A. 可能发生什么,对象是谁以及花费多少成本
B. 通知,相关事件的频率性和时间发生的可能性
C. 风险的成本,特征和控制
D. 质量、风险计划、风险事件的全部数量
E. 风险事件、发生的可能性、风险发生后所带来的价值

4. A risk is defined as what might happen to the_______ of the project
A. assessment
B. detriment
C. schedule
D. cost
E. scope

风险事件被定义为发生在项目__________
A. 评估
B. 损害
C. 时间安排
D. 成本
E. 范围

5. When is the project’s amount at stake the lowest?
A. Conceptual
B. Design
C. Close-out
D. Implementation

什么时候项目的风险所导致的代价最低:
A. 概念
B. 设计
C. 收尾
D. 实施

PMP考试练习答案(风险管理):1-5 EEDBA