PMP考试练习题目(21-25)-项目沟通管理
项目沟通管理-PMP考试章节练习(21-25题) 21. One of the engineers on your team performs a presentation to a perspective client about a proposed design. In answering questions, the engineer reveals that she does not agree with the way in which this system is engineered during the presentation. What are your options as project manager of the engineer, listening to the presentation? 你的项目团队中的一位工程师对一个客户建议的设计进行了一次介绍。在回答问题时, 工程师表示他对系统的设计是不同意的。你作为这个工程师的项目经理在听了介绍后如何反应? 22. It is a few months before the project is scheduled to end. Carol was just hired to take the place of Bob who has moved on to a new assignment. Neither you nor anyone on your team has worked with Carol until now. What type of meeting should take place to introduce Carol to her new responsibilities and handoff of the ongoing work? 还有几个月项目就要完成了。Carol 被委派到项目中来代替Bob 的工作,Bob 分配到新的任务中去了。你和你们团队中的其他人都没有和Carol 一起工作过。在这种情况下开什么类型的会来向Carol 介绍他的新任务并进行工作的移交? 23. You are managing a large project that requires part of your project team to live in other countries with vast differences in time zones. There are a large number of your project team members that are also scattered around a large geographical region of your country. Select the best method of team communications from the items listed below. 你在管理一个大型的项目,这个项目需要部分项目团队成员住在分散的地区中。项目团队中的大部分成员也分布在你们国家的其他地方。从下面选择出一种团队沟通的最佳方法。 24. The project or phase, after either achieving its objectives or being terminated for other reasons, requires______________ 在项目或阶段完成其目的或者因为其他原因被中止之后,需要_____________ 25. Performance of progress reports organize and summarize the information gathered and present the results of any analysis. What document should formalize the information required for the performance report? 进度报告的编制组织并总结了任何分析结果和所收集的信息。需要什么文档来规格化这个报告? PMP考试练习答案(沟通管理):21-25 CDBAB |