项目沟通管理-PMP考试题目(1-5题)1. Which of the following can cause a communication border?
A. Differing perceptions as to project goals and objectives
B. Insufficient action on the part of the project manager
C. Competition for facilities, equipment, material, manpower, and other resources
D. Personality conflicts between managers and/or other personnel
E. Resistance to change
F. All of the above
下面哪一项会引起沟通障碍?
A. 对项目目标和目的的不同理解
B. 项目经理方面行动的不充分
C. 设施、设备、材料、人力和其他资源的竞争
D. 在经理和/或其他员工之间的个人冲突
E. 对变化的抵制
F. 以上所有
2. Most of the project manager’s external communication links consist of:
A. written documents
B. oral communications
C. tactile contact
D. informal contact
项目经理的大多数外部沟通的联系是由下面哪项组成的:
A. 书面的文档
B. 口头的沟通
C. 战术联系
D. 非正式的联系
3. The internal communication linkage are the most important to the health of the project. Which of the following is one of the major driving forces for effective communication in a project?
A. Optimization
B. Differentiation
C. Selection
D. Integration
内部沟通的联系对于项目的良性运作是最重要的。下面哪点是项目有效沟通的主要驱动力之一?
A. 优化
B. 差异化
C. 选择
D. 整合
4. The critical element in a project’s communication system is the:
A. progress report
B. project directive
C. project manager
D. customer
在项目沟通系统中的关键因素是:
A. 进展报告
B. 项目指示
C. 项目经理
D. 客户
5. System integration consists of:
A. assuring that the pieces of a project come together at the right time
B. planning for contingencies that may occur throughout the life cycle of the project
C. the pieces of the project function as an integrated unit
D. A andC
系统整合包括:
A. 确保项目的每一部分在适当的时候集中在一起
B. 制定在项目生命周期中可能发生的应急计划
C. 项目的各个部分以一个整体运作
D. A 和C
PMP参考答案(沟通管理): 1-5 FADCD