PMP考试题----项目人力资源管理题目11-15:11. In order for project managers to be effective, they must:
A. Continue to be actively involved in their technical field of expertise
B. Actively participate with other management personnel in planning the project
C. Monitor and control all task of the project to the lowest level of the WBS
D. Control the functional manager’s personnel on all project aspects
为了使项目经理的工作更有效,他们必须:
A. 继续热情的专注于专业技术领域
B. 主动与其他的管理人员一起编制项目计划
C. 检查控制WBS 最底层的所有工作
D. 控制项目的各个方面职能型经理下属的人员
12. What is the process that the project manager uses to coordinate the efforts of workers toward the accomplishment of group(project) goals?
A. Integration of skills
B. Procurement management
C. Leadership
D. Problem solving
为了努力完成项目目标,项目经理经常用来协调项目人员投入的过程是什么?
A. 整合技能
B. 采购管理
C. 领导能力
D. 解决问题的能力
13. Which of the following is NOT critical action for the project manager to take in the integration process for a matrix organization?
A. Planning for integration
B. Development of an integrated WBS, schedule, and budget
C. Provide technical training for the project team members
D. Resolve customer problems
项目经理在对矩阵型组织实施一个整合过程时,下面的哪个做法不是关键的:
A. 整合计划
B. 制定集成的WBS,日程安排和预算
C. 为项目成员提供技术培训
D. 解决客户的问题
14. Which of the following is NOT a form of power that the project manager can use due to the position of project manager in the company?
A. Formal
B. Reward
C. Penalty
D. Expert
在公司里,下面哪个不属于项目经理在其职位上可以行使的权力?
A. 正式的权力
B. 奖励权
C. 处罚权
D. 专家权
15. Which of the following is NOT an organizational form?
A. Functional organization
B. Matrix organization
C. Projectized organization
D. Project expediter
下面的哪个不属于组织的形式:
A. 职能型组织
B. 矩阵型组织
C. 项目型组织
D. 项目联络人
PMP考试题的参考答案: 11-15 BACDD