11. There are specific absolute for a comprehensive quality program. These are:
A. WBS
B. Fitness for use
C. Involvement during the planning phase
D. Fitness for purpose
E. B andD

全面质量计划可以明确为:
A. 工作分解结构
B. 适用
C. 在计划阶段的参与
D. 符合目的的
E. B 和D

12. Quality control in the final analysis is:
A. Using the technical procedures of monitoring project results to decide if the outputs meet the requirements
B. A production system
C. An inspection system
D. Fitness for purpose

最后分析的质量控制是:
A. 采用技术流程来检测项目结果以确定输出是否符合要求
B. 生产系统
C. 监测系统
D. 符合目的的

13. A firm must produce a product, a service, or a combination of both at:
A. a higher quality than its competitors
B. least an equal quality and at a price equal or lower than its competitors
C. a higher quality and a higher price than its competitors
D. a lower price and lower quality, but at a higher production volume than its competitors

一个公司生产的产品,服务或者两者的结合必须:
A. 比它的竞争对手的质量高
B. 至少在质量上与竞争对手相当,在价格上等于或者低于竞争对手
C. 比它的竞争对手在质量和价格上要高一些
D. 低廉的价格以及略低的质量,但是比竞争对手有较高的生产数量

14. Quality costs include:
A. the total of all costs incurred to assure the production and delivery of acceptable products and services
B. only costs classified as prevention, detection, and corrective action
C. only the cost of scrap, rework due to defects, customer returns and warranty costs
D. the expense of upper management

质量成本包括:
A. 包括发生在确保生产和提交可接收产品和服务方面的所有成本
B. 只用于防止、检查和纠正上的成本
C. 用于废品、由于缺陷而进行的返工、客户退回的产品和担保的成本
D. 高层管理的消费

15. Many accounting systems fail to provide necessary data for management of quality costs and losses because:
A. they fail to clearly and separately identify specific cost elements such as the costs of receiving inspection, production inspection, failure analysis, scrap etc.
B. they focus on collecting and reporting departmental financial information on a summary level
C. they fail to identify each quality cost element as a cost or a loss, so that this information may be summed at every organizational level where quality decisions are made
D. AandC
E. A,BandC

很多会计系统不能提供必备的数据用来管理质量成本和损失,这是因为:
A. 他们不能清楚、独立的区别出特定的成本元素,如接受减产、生产检查、失败分析和废品等的成本
B. 他们关注于在一个综合的层次进行部门财务信息的收集和报告
C. 他们无法对每个质量成本元素的成本或者损失进行区分,所以信息就会在决策的每个组织层面进行汇总
D. A 和C
E. A,B,C

PMP认证考试题参考答案: 11-15 EABAE

阅读本文的人还阅读了:
1、PMP考试难吗? 
2、PMP认证报名条件
3、PMP考试费用是多少?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库