PMP考试题库之项目时间管理21-25题:

21. If task A has seven days of free float and 15 days of total float and the early start date is delayed 5 days, what does this do to the completion date of the project?
A. Delays the end date 10 days
B. Delays the early start date of the next dependent task five days
C. Allows the project to finish five days earlier
D. The finish date doesn’t change
如果任务A 有7 天的自由浮动时间和15 天总浮动时间,并且最早开始时间延误了5 天,这对项目的完成日期有何影响?
A. 完成时间延迟10 天
B. 使下一个相关的活动的最早开始时间延误5 天开始
C. 项目的完成时间提前5 天完成
D. 完成时间不变

22. If Task B has 15 days of free float and 25 days of total float, and the early start date of Task B is delayed 30 days, how is the project affected?
A. The next dependent task’s start date will be delayed 15 days
B. This task will be dropped off the critical path
C. The duration of the task will be shortened 15 days
D. The completion date of the project will be pushed out 5 days
E. A andD
如果任务B 有15 天的自由浮动时间和25 天浮动时间,任务B 的最早开始时间延误了30天,那么项目受什么样的影响?
A. 下一个相关任务的开始时间将延迟15 天
B. 这个任务将不会成为关键路径
C. 任务的工期将缩短15 天
D. 项目的完成时间延长5 天
E. A 和D

23. If task C has 0 days of free float and 0 days of total float, what does this mean to the project?
A. The project does not have adequate lead and lag times built in
B. The task is on the critical path
C. The duration of the task should be compressed
D. The dates for the task are not accurate
如果任务C 有0 天自由浮动时间和总浮动时间,那么这对于项目意味什么?
A. 项目没有提前和滞后的时间
B. 这个任务是在关键路径上
C. 这个任务的工期应该压缩
D. 任务的日期不准确

24. A master schedule is developed for an executive presentation. What information must the PM gather to complete this schedule?
A. Dates of major activities
B. Summary level task budgets
C. Key milestones
D. Summary level task descriptions
E. A.C,D
控制性进度是用于主管进行演示的。为了完成这一计划,项目经理必须要得到什么样的信息?
A. 主要活动的日期
B. 概要任务的预算
C. 关键里程碑
D. 概要任务的描述
E. A,C,D

25. What is one of the key problems with using crashing rather than fast tracking to compress project duration?
A. Personnel overlap
B. Budget constraints
C. Sub-dividing critical path tasks to work in parallel
D. Finish to start relationships are modified
E. Negotiating reduction of task durations
用赶工而不是快速跟进来压缩项目工期的一个主要应该关注的问题是什么?
A. 人员重叠
B. 预算限制
C. 子关键路径任务的并行工作
D. 完成一开始关系的变动
E. 协商缩短任务历时

PMP认证考试题参考答案:21-25  DEBEB