PMP考试题库之项目时间管理16-20题:

16. Timely decisions directly affect the ability of the project team to meet commitments to cost and schedule constraints. Therefore:
A. the project team must be able to make decisions or obtain fast decisions from upper management
B. functional departments should make their decisions as quickly as possible
C. upper management should communicate decisions to the project team at least weekly
D. since consensus decision making is time consuming, provisions have been made for budget and schedule revisions
E. AandC
及时的决策直接反映了项目团队完成成本和进度要求的能力。因此:
A. 项目团队必须能够做出决策或者从高层管理获得快捷的决策
B. 职能部门应该尽快的做出决策
C. 高层管理应该至少每周与项目团队进行沟通
D. 因为取得大家的一致同意是费时间的,只要按时在预算内提供就可以
E. A 和C

17. For a well planned project the project schedule is:
A. The agenda for carrying out the plan or a portion of it
B. Not important, as each team member acts according to plan
C. Used to generate a time table of major commitments for the project
D. B andC
对于一个计划良好的项目,项目进度是
A. 实施计划或者其中一部分的日程安排
B. 不重要,因为每个团队成员按照计划行动
C. 用于生成一个项目主要交付物的时间表
D. B 和C

18. The project plan is developed by:
A. The project manager
B. The manager of project managers
C. The project team
D. Top management
E. A andC
项目计划是由______ 制定的:
A. 项目经理
B. 项目经理的上层经理
C. 项目团队
D. 高层管理
E. A 和C

19. Planning and scheduling are:
A. Separate and distinct tasks and have little relationship to each other
B. The only means for assuring project resource
C. Distinct but inseparable aspects of the successful project
D. Tasks which take place in parallel in a project environment
计划和进度安排是:
A. 是独立的,有各自的任务,并且之间没有什么关系
B. 是确保项目资源的唯一方法
C. 区别的,但是一个成功项目不可分割的方面
D. 在项目环境中并行发生的任务

20. The Time Management Function as it relates to personnel:
A. refers primarily to the manner in which the project manager and the various functional contributors to the project manage their time on a daily basis:
B. should not be over emphasized because it develops a “clock-watching” mentality in the project team.
C. Consists of four overlapping processes: planning, estimating, scheduling, and controlling
D. Consists of two overlapping processes: planning and controlling
与人有关的时间管理功能:
A. 首先指项目经理和其他各职能人员在项目中管理他们日常时间的方式
B. 不要过分强调,因为会在团队中养成“等着下班时间到来”的一种习惯
C. 包括了四个重叠的过程:计划、估算、进度安排和控制
D. 包括了两个重叠的过程:计划和控制

PMP认证考试题参考答案:16-20 ACECC