第11章PMP练习题-第四部分(PMP考试复习题)
31.Assuming that the ends of a range of estimates are ±3 sigma from the mean, which of the following range estimates involves the least risk? 32.A project manager has just finished the risk response plan for his project. Which of the following should he do next? 33. You are using information-gathering techniques to identify project risks. It’s very important that you keep biases to a minimum. Which technique should you use? 34. You are working on a research and development project in the agriculture industry. Your risk management team has identified several risks and has determined that the most significant risk to the project is a financial risk. The most effective response for this type of risk is: 35. Your project team has identified several risks related to your project. You decide to take actions to reduce the impact of a particular risk event by reducing the probability of its occurrence. What risk response strategy are you using? 36. _____sometimes called risk symptoms or warning signs, are indications that some risk has occurred or is about to occur. 37. When managing a new project development project, a technical issue hinders the progress, you decide to invite experts and use Delphi Technique. You should: 38.The first requirement for effective risk management is 39. Sensitivity analysis: 40.Decreasing the probability of a risk is an example of risk: |