第10章PMP练习题-第四部分(PMP考试章节复习)
31. Which of the following is most appropriate for face-to-face communication? 32. A project has several teams. Team A has repeatedly missed several deadlines in the past. This has caused Team B to have to crash the critical path several times. As the project leader for Team B,you should_____ 33. You have a project team consisting of people from four countries. The project is very important to the company and the project manager is concerned about its success. The length of the project schedule is acceptable. What type of communication methods should you use? 34.Barriers can influence communication when sending or receiving information. Which of the following is NOT a barrier? 35. The project status meeting is not going well. Everyone is talking at the same time, there are people who are not participating and many topics are being 36. Your project is well into the execution phase and remains on time, on budget and on specification. This morning, your project sponsor called to express concern about the project. Based on the schedule baseline, the project should be nearing implementation, but the sponsor does not know the current status of the project. You remind the sponsor that your team produces a detailed status report weekly and distributes it via e-mail. The sponsor indicates that e-mil is too impersonal and verbal updates are preferred. This situation suggests problems with which of the following project management processes? 37. A project manager has just been assigned a team that comes for many countries including Brazil, China, the US and Britain. What is her BEST tool for success? 38.A project team was composed of 5 member .five more members additionally joined to this team. what are the communication channels added? 39.You prepared an integrated project plan and a project schedule. You submitted it to the steering committee, and it was approved. Key stakeholders accepted the plan. It is time to distribute it. Both the project plan and schedule should be distributed to 40. A project team has members in 4 different locations with varying information systems. The project manager works with the project team. To determine how project information will be distributed, these methods are detailed in which document? |