第七章PMP复习题-第1部分(PMP章节练习系列)
1.The cumulative CPI has been shown to be relatively stable after what percentage of project completion? 2. A project is considered complete when –- 3. The project sponsor told the PM that he wanted to cut the 6 month project to 3 months by doubling the number of resources. The PM was experienced enough to know this would NOT work because of— 4. You need to decide between two alternatives. You can either hire a contractor to build one of the project’s deliverables, or you can buy the deliverable from an overseas supplier. Both options require acquisition, operating, and disposal costs that you compare between the two alternatives to make a decision. What is this technique called? 5.In order to establish the budget,all of the following needs to evaluated except: : 6.某人刚刚被任命为某项目的项目经理,正在指导项目计划的编制工作。你是该项目的关键干系人之一,你想要立即拿到项目的成本预算,但项目经理没有给你。最可能的原因是: 7. 副总裁给你打来紧急电话,说她15 分钟后要去见一个重要的客户,谈一个很大很复杂的关于网站的项目。她给你30 秒钟的时间考虑,然后告诉她这个项目需要多少成本。你迅速地回顾过去的类似项目,虽然有些信息尚未知晓,但你还是给了她一个大概的数字。你刚才使用的是什么类型的估计方法? 8.Which of the depreciation methods offers the least tax advantage? 9. There are two projects to choose between: Project A with an NPV of US $45,000; or Project Bwith an NPV of US $85,000. What is the opportunity cost of selecting project B? 10.A project is seriously delayed. Earned value analysis shows that the project needs to be completed 10% faster than the work has been going. To get the project back on track, management wants to add 10 people to a task currently assigned to one person. The project manager disagrees, noting that such an increase will not produce an increase in speed. This is an example of: |