第6章PMP练习题-第四部分(含答案-PMP考试题系列 )

转载者:PMP团购网      发布时间:2013/11/7        点击: 4870

31.In attempting to complete the project faster, the project manager looks at the cost associated with crashing each task. The BEST approach to crashing would also include looking at the:
A. Risk impact of crashing each task
B. Customer’s opinion of what tasks to crash
C. Boss’s opinion of what tasks to crash and in which order
D. Project phase in which the task is due to occur
31.为更快完成项目,项目经理研究与每项活动赶工相关的费用。为得到更好的赶工方法,还应关注:
A. 对每项活动赶进度的风险影响
B. 客户针对什么活动进行赶进度的意见
C. 领导针对什么活动进行赶进度以及采取何种次序的意见
D. 活动发生的项目所在阶段
参考答案:A。赶工会导致风险。参见《PMBOK 指南》第五版第

32. Which of the following are GENERALLY illustrated BETTER by bar charts than network diagrams?
A. Resource trade-off
B. Critical paths
C. Logical relationships
D. Progress or status
32.总的说来,下面哪个选项在横道图中比网络图中能得到更好的图示?
A. 资源权衡
B. 关键路线
C. 逻辑关系
D. 进展或状态
参考答案:D。甘特图可表示时间,不表示逻辑关系。网络图表示逻辑关系,不表示时间。参见《PMBOK 指南》第五版第182 页、159 页

33. Five tasks are scheduled to be completed in sequence. Each task has a finish-start relationship with the next task. Each has one day of total float. As of today,
task-1 and task-2 have been completed on schedule. How many days of float remain in the schedule for these tasks?
A. One
B. Two
C. Three
D. Zero
33. 五项任务按照顺序排列着。每一个任务与另一个任务都是结束-开始的关系。每一
个任务只有一天
的总时差。到了今天,任务1 和任务2 按进度完成了。按照进度,剩余任务的时差是多
少天?
A. 一天
B. 二天
C. 三天
D. 0天
参考答案:A。每个任务有一天的时差,任务1 和任务2 按进度完成,说明没有动用时差,后续任务的时差还是1 天。

34.The critical path time needs to be reduced by 20% .you may take the following actions except:
A.Adding resources
B.Crashing time schedule
C.Eliminating float
D.Paralleling activities
34.当需要减少20% 关键路径时间时,你可以采用下列的行动,但()除外:
A.增加资源
B.压缩时间
C.消除浮动时间
D. 并行安排活动
参考答案:C。选项A、B、D 是进度压缩方法。参见《PMBOK指南》第五版第181 页

35.An Activity-On-Node (AON) project diagram shows the following activities on two critical paths,D-E-J-L and D-E-G-I-L. Each activity is at least three days in duration, except for the activity L that is one day in duration. If you are directed to reduce the project by one day, which activities are MOST likely to change?
A. L
B.E or J
C.G or I
D.D or E
35.一个AON 图显示了在两个关键路径上的下列活动:D-E-J-L 和D-E-G-I-L。除了L历时为1 天外,其他每个活动有最少3 天历时。如果你计划减少这个项目历时1 天,哪个活动最可能被修改?
A. L
B.E 或J
C.G 或I
D.D 或E
参考答案:D。有二条关键路径,要减少1 天的历时,那么应该修改共同的活动:D 或E或L。但活动L 只有1 天,进度压缩是不改变范围的,排除活动L。那么就只有活动D或E 了,即选项D

36.You are a project manager for a new product development project that has four levels in the work breakdown structure, and has been sequenced using the precedence diagramming method. The duration estimates have been compressed and a schedule created. What time management activity would you do NEXT?
A. Begin schedule control
B. Gain approval
C. Analogously estimate the schedule
D. Begin resource planning
36. 你是一名负责一个新产品开发项目的项目经理,该项目的WBS 有四级,并已用紧前关系绘图法进行了活动排序。活动持续时间估算已经被压缩,并完成了进度表编制。下一步你该进行什么时间管理活动?
A. 开始进度控制
B. 获得批准
C. 类比估算进度
D. 开始资源规划
参考答案:B。进度计划制定好后,应该获得批准,成为进度基准

37.As for Critical Chain Method,which of the following is NOT proper?
A. Critical path is not calculated in Critical Chain Method.
B. Critical Chain Method focuses on controlling buffers rather than critical paths.
C. Critical Chain is constrained by resource availability.
D. Critical Chain Method generally uses smaller duration estimates than those in Critical Path Method.
37.对于关键链法,下面哪项是不合适的?
A. 关键路径不是在关键链法中计算出来的
B. 关键链法关注于控制缓冲而不是关键路径
C. 关键链受到所获资源的约束
D. 关键链法通常比关键路径法中使用更少的历时估算
参考答案:A。关键链法中有关键路径的。参见《PMBOK 指南》第五版第178 页

38.A project manager is scheduling a project where the performing organization has currently many projects and there are serious resource conflicts among other projects.In this environment, which tool is the least effective?
A.Critical Chain Method
B.Reverse resource allocation
C.CPM
D.Simulation
38.项目经理正在安排一个项目进度,与此同时公司有几个同时进行的项目,并且该项目与其他项目之间存在着严重的资源冲突,在此情形下,哪个工具最无效?
A. 关键链方法
B. 储备资源分配
C. 关键路径法
D. 模拟
参考答案:C。关键路径不考虑资源制约。参见《PMBOK 指南》第五版第176 页

39.Decomposition is a technique used for both create WBS and define activity . Which statement best describes the role decomposition plays in define activity as compared to create WBS?
A. Final output is described in terms of work packages in the WBS.
B. Final output is described as deliverable or tangible items.
C. Final output is described as activities or action steps.
D. Decomposition is used the same way in create WBS and activity definition.
39.分解是一种既可用于创建WBS,又可用于定义活动的技术。同创建WBS 相比,下列哪项陈述最好地描述了分解在定义活动中发挥的作用?
A.最终输出是用WBS 中的工作包来说明的。
B.最终输出被描述为可交付成果或有形产品.
C.最终输出被描述为活动或行动步骤
D.分解在创建WBS 的用途与在定义活动中的用途完全相同
参考答案:C。参见《PMBOK 指南》第五版第151 页

40.You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. It also requires the use of kryptonite bolts to assemble the piping system. Because kryptonite has a mass density that is 16 times its weight, the pipe must be resting in the ground a total of 10 days before the bolts can be installed. In this example, the 10-day period is defined as
A. Lag
B. Lead
C. Float
D. Slack
40.你负责管理一个城市用水系统项目。为了避免水管生锈,合同上要求使用铁合金的管道设备,此外还要用不锈钢铆钉来组装这些管道。根据某些技术要求,这些管道放置好以后要过10 天才能装铆钉。这10 天被称作:
A. 滞后时间
B. 前置时间
C. 浮动时间
D. 松弛时间
Unlike bar charts, milestone charts show____
A. Scheduled start or completion of major deliverables and key events
B. Activity starts and end dates
C. Expected durations
D. Dependencies

参考答案:A。滞后时间的定义。参见《PMBOK 指南》第五版第159 页