1. Velidate scope is a (an)
A. Planning process
B. Executing process
C. Monitoring and controlling process
D. Closing process
1. 确认范围是一个
A. 规划过程
B. 执行过程
C. 监控过程
D. 收尾过程

2. Perform quality assurance is a (an)
A. Planning process
B. Executing process
C. Monitoring and controlling process
D. Closing process
2. 实施质量保证是一个
A. 规划过程
B. 执行过程
C. 监控过程
D. 收尾过程

3. Control quality is a (an)
A.Planning process
B.Executing process
C.Monitoring and controlling process
D.Closing process
3.控制质量是一个
A. 规划过程
B. 执行过程
C. 监控过程
D. 收尾过程

4. The Project Procurement Management knowledge area includes all of the following EXCEPT:
A. Conduct procurements
B. Close procurements
C. Identify risks
D. Plan procurement management
4. 项目采购管理知识领域包含下面的过程,除了:
A. 实施采购
B. 结束采购
C. 识别风险
D. 规划采购管理

5. All the following are true EXCEPT?
A. The project manager needs to determine the skills of the stakeholders.
B. The stakeholders’ impact on the project must be assessed.
C. The stakeholders do not have a role in determining the project plan unless they are part of theproject team.
D. Stakeholder management is part of the project plan.
5. 下面哪项说法不正确?
A. 项目经理需要判断项目干系人的技能
B. 项目干系人对项目的影响必须被评估
C. 在决定项目计划时不需要考虑项目干系人,除非他们是项目团队的一部分
D. 项目干系人管理是项目计划的一部分

6. Which of the following is the most proper?
A. A project charter is developed based on the preliminary project scope statement
B. Planning activities will start after the finish of initiating process group
C. Business needs are documented in the initiating processes,but project objectives are determined in the planning processes
D. At the time initiating process group occurs,planning activities also occur.
6. 下列哪一项是最合适的描述
A. 项目章程的制定是基于初步项目范围说明书
B. 计划活动开始于启动过程组完成之后
C. 商务需求是在启动过程进行文档描述,但是项目目标是在计划过程确定的
D. 在启动过程进行时,计划活动也在进行

7. The first phase of a project is the feasibility study.According to the PMBOK,which of the project management process group does the feasibility study phase need?
A. Planning
B. Planning , monitoring and controlling
C. Initiating and closing
D. Alln of five process groups
7. 项目的第一阶段是可行性研究,根据PMBOK,可行性研究阶段需要下面哪个项目管理过程组?
A. 计划
B. 计划和监控
C. 启动和收尾
D. 所有5个过程组

8. Project management processes ensure the effective flow of the project throughout its existence. Product-oriented  processes specify and create the project's product. Therefore, project management process and product-oriented process
A. Overlap and interact throughout the project
B. Are defined by the project life cycle
C. Are concerned with describing and organizing project work
D. Are similar for each application area
8. 项目管理过程确保项目自始至终顺利进行。 产品导向过程说明并创造项目产品。 因此项目管理过程和产品导向过程:
A. 是重叠的并且在整个项目期间是交互影响的
B. 由项目的周期决定的
C. 与对项目工作的描述和组织有关
D. 在每个应用领域都是类似的

9. Project management processes can be categorized into five groups. The process groups are linked by the results they produce. The outputs of one often become the input to another. What is the MOST appropriate sequence of the five project management process groups?
A. Initiating-planning-monitoring and controlling-executing-closing
B. Initiating-executing-monitoring and controlling-planning-closing
C. Initiating-planning-executing-monitoring and controlling-closing
D. Initiating-monitoring and controlling-planning-executing-closing
9. 项目管理过程可以划分成5组。这5个过程通过它们产生的结构衔接起来,一个过程组的成果变成了另一个过程组的依据。这5个管理过程组最恰当的排序是什么?
A. 启动-规划-监控-执行-收尾
B. 启动-执行-监控-规划-收尾
C. 启动-规划-执行-监控-收尾
D. 启动-监控-规划-执行-收尾

10.  Within each process group, individual processes are linked by
A. The project manager.
B. Outputs.
C. Exit points
D. Chains
10. 每个过程组内,单个过程的衔接是通过:
A. 项目经理
B. 输出
C. 出口点
D. 链


PMBOK指南(第5版)第三章习题 参考答案

1.
参考答案:C
知识要点:项目管理过程组与知识领域
资料来源:《PMBOK指南》第5版第61页,或培训讲义第45页

2.
参考答案:B
知识要点:项目管理过程组与知识领域
资料来源:《PMBOK指南》第5版第61页,或培训讲义第45页

3.
参考答案:C
知识要点:项目管理过程组与知识领域
资料来源:《PMBOK指南》第5版第61页,或培训讲义第45页

4.
参考答案:C
知识要点:项目管理过程组与知识领域
资料来源:《PMBOK指南》第5版第61页,或培训讲义第45页

5.
参考答案:C
知识要点:制定项目管理计划,要鼓励所有干系人参与
资料来源:《PMBOK指南》第5版第56页,或培训讲义第47页

6.
参考答案:D
知识要点:项目管理五大过程组是交叉重叠的
资料来源:《PMBOK指南》第5版第51页,或培训讲义第43页

7.
参考答案:D
知识要点:在每个阶段中,会执行项目管理五大过程组
资料来源:《PMBOK指南》第5版第52页,或培训讲义44页

8.
参考答案:A
知识要点:项目管理过程和产品导向过程是重叠的
资料来源:《PMBOK指南》第5版第48页,或培训讲义第40页

9.
参考答案:C
知识要点:五大项目管理过程组的相互作用
资料来源:《PMBOK指南》第5版第53页,或培训讲义第43页

10.
参考答案:B
知识要点:一个过程的输出会成为另外一个过程的输入
资料来源:《PMBOK指南》第5版第52页,或培训讲义第41页