PMP考试每天一练-2020年PMP考试练习题145
PMP考试练习题一: During project execution, a project falls behind schedule. After evaluating options, the project manager concludes that temporarily collocating the most active virtual team members could bring the project back on schedule.What is the project manager doing? A. Developing the project team B. Managing the project team C. Optimizing the project team D. Balancing the project team 在项目执行期间,一个项目落后于进度计划。在评估方案之后,项目经理得出结论,暂时让最活跃的虚拟团队成员集中办公能让项目恢复进度计划。项目经理执行的是下列哪一项? A.建设项目团队 B.管理项目团队 C.优化项目团队 D.平衡项目团队 PMP考试答案解析:集中办公是建设项目团队的工具。 PMP考试参考答案:A PMP考试练习题二 A team member versa unable to attend the last project review meeting. The project manager confirms with the team reamer by phone that the project icon track and on budget. What should the team member consult to determine what task to perform next? A. Activity management plan B. Task management plan C. Project schedule D. Project calendar 一名团队成员不能够参加上一次项目评审会。项目经理用电话与该名团队成员确认项目符合进度和预算。团队成员应查阅下列哪一项来确定下一步要执行什么任务? A.活动管理计划 B.任务管理计划 C.项目进度计划 D.项目章程 PMP考试答案解析:从项目进度计划中查看活动的开始、结束以及持续时间,活动间的逻辑关系等。 PMP考试参考答案:C |