PMP考试每天一练-2020年PMP考试练习题143
PMP考试练习题一: A project manager wants to distribute the project charter to project stakeholders. Which method of communication should be used? A. Interactive B. Pull C. Push D. Face-to-face 项目经理希望将项目章程发送给项目干系人。应该使用哪一种沟通方法? A.交互式沟通 B.拉式沟通 C.推式沟通 D.面对面沟通 PMP考试答案解析:将文件发出去,这是推式沟通。 PMP考试参考答案:C PMP考试练习题二 A project management office (PMO) is presented with three project choices for implementation. Project A has an internal rate of return (IRR) of 12%, project B has a schedule performance index (SPI) of 0.8, and project C has a benefit-cost ratio (BCR) of 1.2. Based on this information, which of the following projects should be pursued? A. Project B B. Project C and B C. Project A D. Project C 项目管理办公室(PMO)有三个项目可供选择实施。项目A的内部收益率(IRR)为12%,项目B的进度绩效指数(SPI)为0.8;项目C的效益-成本比(BCR)为1.2。根据这个信息,应选择实施下列哪一个项目? A.项目B B.项目C和B C.项目A D.项目C PMP考试答案解析:项目C的BCR>1,项目可行。 PMP考试参考答案:D |