PMP考试每天一练-2020年PMP考试练习题122
PMP考试练习题一: After completing the project planning, a project manager schedules a phase exit meeting.During this meeting, what should occur? A.Project manager reviews the project team members’ performance B.Project deliverables are reviewed and the decision is made to continue the project C.Senior management analyzes the project manager’ performance D.Project’s lessons learned are documented and the project is closed 完成项目规划之后,项目经理安排了一次阶段结束会议。在这次会议上,会发生什么情况? A.项目经理审查项目团队成员的绩效 B.审查项目可交付成果,并做出继续项目的决定 C.高级管理层分析项目经理的绩效 D.记录项目的经验教训,项目收尾 PMP考试答案解析:题目说的是阶段收尾,B是阶段收尾。选项D是项目收尾。 PMP考试参考答案:B PMP考试练习题二 A project manager is working on a multiyear project. Over time the technology tools and techniques in the industry change, which one of the following should be used to ensure the project produces the highest quality outcome for the customer? A, Cause and effect diagram B. Control charts C. Continuous improvement D. Pareto diagrams 项目经理正在管理一个为期多年的项目。随时间的过去,行业中的技术工具和技术发生了变化。为确保项目能为客户产生最高的质量成果,应使用下列哪一项? A.因果图 B.控制图 C.持续改进 D. 帕累托图 PMP考试答案解析:质量管理的关键是持续改进。 PMP考试参考答案:C |