以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2020年PMP考试练习题98

转载者:PMP团购网      发布时间:2020/7/27        点击: 1852

PMP考试练习题一:

A new product development project is on schedule. At the end of the execution phase, a new law is issued that changes the project’s quality standards. What should the project manager do first?

A.Complete and submit the change request form

B.Communicate the changes to the sponsor

C.Update the project’s scope management plan

D.Negotiate for more funding to keep the project on schedule

一个新产品开发项目符合进度。在执行阶段结束时,一项新法律颁布,更改了产品的质量标准。项目经理首先应该做什么?

A.完成并提交变更请求

B.与发起人沟通变更

C.更新项目的范围管理计划

D.协商获得更多资金,保证项目符合进度

PMP答案解析:新法律颁布,导致更改了产品的质量标准。这是事业环境因素发生了变化,也许会引发项目发生变化。

PMP参考答案:A

PMP考试练习题二

During a construction project, the project manager wants to outsource the building of a boundary wall at the construction site. Prospective vendors are invited to a conference. The architect of the procuring company prepares a cost estimate to construct the boundary wall which is not shared with the prospective vendors. What technique should be used to conduct procurements?

A. Independent estimates

B. Proposal evaluation techniques

C. Expert judgment

D. Screening system

在一个施工项目中,项目经理希望外包施工现场边界墙的建设。潜在供应商受邀参加会议。采购公司的建筑设计师准备了一份边界墙的施工成本估算,但未与潜在供应商分享。开展采购应使用什么技术?

A.独立估算

B.建议书评价技术

c.专家判断

D.筛选系统

PMP答案解析:采用独立估算技术估算出自己的心里价位。

PMP参考答案:A

阅读本文的人还阅读了:
福州PMP考试地点在哪里?
pmp证书有含金量吗?
PMP考试难度?
PMP考试骗局?
PMP考试报名官网是什么?
PMP考试时间及报名时间
pmp教材第六版pdf下载
pmp考试报名费?
pmp认证考试怎么报名?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库