PMP考试每天一练-2019年PMP考试试题117

转载者:PMP团购网      发布时间:2019/9/20        点击: 1804

PMP考试试题一:

A project is dependent upon a vendor's deliverable. However, the vendor cannot deliver the product on time. The customer now wants to replace the project manager.What should the project manager have done to compensate for the late delivery?

A. Monitored using a procurement audit

B. Performed a variance analysis

C. Selected an alternate vendor

D. Responded with a contingency plan

一个项目取决于供应商的可交付成果。但是,该供应商无法按时交付产品。客户现在希望替换掉项目经理。若要补偿延迟交付情况,项目经理事先应该做什么?

A.执行采购审计监督

B.执行偏差分析

C.选择可替代的供应商

D.使用应急计划应对

PMP答案解析:首先执行偏差分析,看看偏差到底有多少。

PMP参考答案:B

PMP考试试题二

A project team conducted a session to define project requirements and collected numerous ideas. What technique should the team use to sort these ideas into groups for review and analysis?

A. Brainstorming

B. Nominal group technique

C. Affinity diagram

D. Mind mapping

项目团队召开一次会议,定义项目需求并收集各种意见。团队应使用什么技术来为这些意见分组,以便进行审查和分析?

A.头脑风暴

B.名义小组技术

C.亲和图

D.思维导图

PMP答案解析:亲和图,用来对大量创意进行分组,以便进一步审查和分析。

PMP参考答案:C

阅读本文的人还阅读了:
长春PMP考试地点在哪里?
哈尔滨PMP考试地点在哪里?
重庆PMP考试地点在哪里?
PMP考试报名怎么做?
国内PMP考试通过率有多高?
PMP考试有题库吗?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库