PMP考试每天一练-2019年PMP考试试题63
PMP考试试题一: In a project meeting, the development team tells the project manager that they have two important concerns: they do not have all the required licenses, and a main programmer was injured and will be unable to work for a month. What should the project manager do first: A. Estimate how these situations will impact the project, and create a change request due to external factors. B. Ask the human resource department for an available programmer, and talk to the procurement department about the licenses. C. Analyze how these situations will impact the project to see if it is possible to assume the cost and risk. D. Check the risk management plan to see if there are planned indications to resolve the issues. 在项目会议上,开发团队告诉项目经理,他们有两个重要问题:他们没有所有必需的许可证,以及一名主程序员受伤,将无法工作一个月。项目经理首先应该做什么? A.评估这些情况将如何影响项目,并创建一份由于外部因素造成的变更请求。 B.要求人力资源部提供一名可用的程序员,并与采购部门讨论相关许可证。 C.分析这些情况将如何影响项目,看看是否可能承担成本和风险。 D.检查风险管理计划,看看是否有计划的指示来解决这个问题。 PMP答案解析:推荐C答案,进行风险分析。D答案中的风险管理计划这个词汇,在PMBOK的术语环境,不会包括任何具体的风险以及应对措施 PMP参考答案:C PMP考试试题二 In a project closure report, a project team discovers risks which were not identified during the project lift cycle. The project team recommends performing a risk reassessment for future project.In which of the following should this recommendation be documented? A. organizational process assets updates B. project reports C. historical information D. risk register updates 在一份项目收尾报告中,项目团队发现在项目生命周期中未识别到的风险。项目团队建议为未来项目执行风险再评估。这项建议应记录在下列哪一项中? A.组织过程资产更新 B.项目报告 C.历史信息 D.风险登记册更新 PMP答案解析:选项A包括了B、C、D PMP参考答案:A |