以下城市均已开通:
关闭
当前位置:PMP团购网 > PMP考试资料 > 正文

PMP考试每天一练-2019年PMP考试试题63

转载者:PMP团购网      发布时间:2019/5/29        点击: 1719

PMP考试试题一:

In a project meeting, the development team tells the project manager that they have two important concerns: they do not have all the required licenses, and a main programmer was injured and will be unable to work for a month. What should the project manager do first:

A. Estimate how these situations will impact the project, and create a change request due to external factors.

B. Ask the human resource department for an available programmer, and talk to the procurement department about the licenses.

C. Analyze how these situations will impact the project to see if it is possible to assume the cost and risk.

D. Check the risk management plan to see if there are planned indications to resolve the issues.

在项目会议上,开发团队告诉项目经理,他们有两个重要问题:他们没有所有必需的许可证,以及一名主程序员受伤,将无法工作一个月。项目经理首先应该做什么?

A.评估这些情况将如何影响项目,并创建一份由于外部因素造成的变更请求。

B.要求人力资源部提供一名可用的程序员,并与采购部门讨论相关许可证。

C.分析这些情况将如何影响项目,看看是否可能承担成本和风险。

D.检查风险管理计划,看看是否有计划的指示来解决这个问题。

PMP答案解析:推荐C答案,进行风险分析。D答案中的风险管理计划这个词汇,在PMBOK的术语环境,不会包括任何具体的风险以及应对措施

PMP参考答案:C

PMP考试试题二

In a project closure report, a project team discovers risks which were not identified during the project lift cycle. The project team recommends performing a risk reassessment for future project.In which of the following should this recommendation be documented?

A. organizational process assets updates

B. project reports

C. historical information

D. risk register updates

在一份项目收尾报告中,项目团队发现在项目生命周期中未识别到的风险。项目团队建议为未来项目执行风险再评估。这项建议应记录在下列哪一项中?

A.组织过程资产更新

B.项目报告

C.历史信息

D.风险登记册更新

PMP答案解析:选项A包括了B、C、D

PMP参考答案:A

阅读本文的人还阅读了:
PMP认证考试的报名条件?
PMP是什么?
PMP考试有什么科目?
上海PMP考试地点在哪里?
广州PMP考试地点在哪里?
深圳PMP考试地点在哪里?
香港PMP考试地点在哪里?

网站更新

合作与联系

PMP团购导航
远程PMP团购
北京PMP团购
上海PMP团购
广州PMP团购
深圳PMP团购
江浙PMP团购
西部PMP团购
其他城市团购



PMP题库